| |
|
 |
Frequently Asked Questions
- Contract with OPA is executed on the connection date of the project provided
that the microFIT contract offered by OPA has been accepted within 15
business days.
- The contract with the OPA will be held by AGRIS Solar Co-operative.
- Transfer of Contract – microFIT Contracts maybe assigned to the Co-op,
AGRIS will have to make application to the OPA on behalf of the member.
Consent to assignment is at the sole discretion of the OPA.
- Insurance – Coverage is as follows: Wind, Hail, Fire, Lightning, Explosion,
Storm, Business Interruption in the event of damage to system as a result of an
insurable event.
- Power production of the system – OPA rules for microFIT apply to the power
production of the inverter or the maximum allowable output to the grid, which
cannot exceed 10kw. The Ministry of Environment evaluates the surface area
of power production not the inverter output. If the Ministry audits your site and
determines that the panels in aggregate are over the 10kw then you are no
longer adhering to the rules as defined by the microFIT contract and will be
subject to Renewal Energy Assessment.
System
- Power for internal processes is via the units own solar generation, there is
no requirement for Grid feed, each unit will have a 120v service circuit off
the 208/240v primary side of the disconnect. That 120v circuit will power
tracker operation and onboard battery backup system (for instances where the
inverters have to shutdown due to loss of grid connectivity)
- Location – system must be located in an area which captures the greatest
degree of sun exposure, the unit array travels in an arc of approximately 240
degrees from east to west.
Electrical
- Transformers – if the LDC determines that a transformer upgrade or install is
required then that cost would be born by the Co-op. In these situations analysis
will be completed by Spark to determine the economics before proceeding
with installation.
- Poles & Pole Lines – the LDC will make the determination if a new pole or pole
relocation is required, in order to provide access to the grid. In most cases any
new poles would be installed within the municipal road boundary, it would
be the Co-op’s responsibility to get wire run to that location. In these situations
it would be Spark/Northwind’s intent to bury wire up to the pole location
(municipal boundary or “fenceline”). In all cases Spark/Northwind would
consult with the property owner before installation commences.
- Distance of Solar system from connection point – maximum distance from
the system to the hydro connection point should be 500’ for instances where
distances are greater there would be additional site review.
- Connection – Connections will be Parallel, as defined by the LDC, in some
circumstances connections maybe direct, where the PV system is connected to
the grid at a location which is not in or around your existing farm buildings. As
the connections tend to be more expensive to make , sites where this may occur
will require review by AGRIS Solar and Northwind.
- Phasing – units will work with single phase or three phase. If your farm has three
phase power the LDC will make a determination as to which phase would be
the best for the connection point (in most cases the phase that is loaded the
most will be the connection point).
Construction/Maintenance
- Access – Construction – Spark/Northwind will require access to the location of
the system for gravel and concrete delivery and erection of the unit. Excavation
will be conducted primarily by mini excavator and erection of components will
be conducted via 2 ton truck mounted cranes, in order to minimize impact to
site. Excavation of buried conduit/wire will be as per Electrical code. Depth of
bury will be 30” in most cases.
- Excavated material must remain on the farm, AGRIS Solar is not allowed to
remove material without proper environmental assessments being completed.
- Procedure – Excavation of topsoil and subsoil to a depth of approximately
4’. Excavation is backfilled with Granular material and compacted to spec.
Concrete base is formed and poured the next day along with the mounting pole
installation. Concrete is allowed to cure for approximately two weeks. Once
curing has occurred mounting of the tracker frame, inverters and panels take
place along with wiring and connection to the generation meter base. After the
system is inspected and passed by the ESA, the LDC will make connection to
the grid.
- Maintenance – once per year a service technician will visit the site to perform
scheduled service tasks, these visits will be walk in visits. In the event that major
damage occurs to a unit (ie. as a result of major wind damage) vehicle access
to conduct repairs maybe required.
- In all cases Northwind/Spark forces will contact the property owner before
commencing work and will keep the owner apprised of all work activities
throughout the process.
Process
- Information required to process your application – Name and legal description
of property, PIN number if available, mailing address, phone number, email
address, contact information.
- Once you have made the decision to join AGRIS Solar Co-operative (please
see the “3 Easy Steps to Join”) the process would be as follows;
- Upon purchasing your membership share and signing a licence agreement
AGRIS Solar will make application to the OPA and LDC for the respective
contracts.
- Upon your review of the Offering Statement and your wish to purchase
a preference share in AGRIS Solar, an AGRIS Solar representative will
make arrangements to visit your farm to conduct a site review and finalize
the documentation process.
- After concluding the site review and deciding on the final location of the
system AGRIS Solar will begin the process to finalize the construction and
installation of a system on your farm.
- When all the system components are ready to be installed on your farm
you will be contacted to discuss installation timing and proceed.
- Timing – OPA and LDC applications take approximately 30 to 60 days
for review, equipment deliveries are approximately 60 days from the time
AGRIS places an order, the installation process takes approximately 7
days in on site time.
|
|
|